Why does the slab matter for a mezzanine floor?
The existing ground floor slab acts as the foundation for a mezzanine floor, because every load on the mezzanine ends up concentrated at the foot of its columns.
A ground-bearing slab is normally designed to carry loads spread across its surface, passing them fairly evenly to the ground beneath. A mezzanine changes that. The weight of the deck, the goods stored on it, the people and equipment using it and the steel frame itself are gathered into a small number of point loads, one at each column base. The slab has to carry each of those loads safely.
This is a legal requirement as well as a practical one. Requirement A1 of the Building Regulations requires that loads are “sustained and transmitted by it to the ground safely”, and building control will expect evidence that the slab is adequate before approving the design.
What determines whether a slab can carry a mezzanine?
A slab’s capacity to carry a mezzanine is determined by how it was built and what it sits on.
- Thickness. A thicker slab spreads a point load over a wider area. The Concrete Society notes that “thickness variations can be very important for the performance of a slab”, so thickness is measured rather than assumed.
- Concrete strength. Stronger concrete resists bending and local failure under a column base.
- Reinforcement. Whether and how the slab is reinforced affects its resistance to bending and cracking.
- Joints and edges. Slabs are cast in bays separated by joints. A column base close to a joint or a slab edge has less concrete around it to share the load.
- The ground beneath. The slab relies on the sub-base and soil beneath it. Weak, variable or compressible ground increases the risk of settlement.
- Existing loads. Racking, machinery or other point loads already on the slab near proposed column positions reduce the capacity left for the mezzanine.
What does an engineer check?
An engineer checks whether the slab can resist each column load in bending, in punching and across joints, and whether the ground beneath will settle.
- Bending under point loads. Whether the slab can carry the column load without cracking or bending excessively.
- Punching. Whether the column base could push through the slab locally, which is known as punching.
- Load transfer across joints. Whether loads near a joint are adequately shared with the neighbouring bay.
- Settlement. Whether the ground will compress unevenly under the new loads.
In the UK these checks are generally based on the Concrete Society’s Technical Report 34, Concrete industrial ground floors, which sets out design methods for point loads, punching and load transfer across joints. The checks use the actual column loads from the mezzanine design, so the slab assessment and the mezzanine design are carried out together rather than one after the other.
How is an existing concrete slab assessed for a mezzanine floor?
The capacity of an existing slab is established first from construction records and, where records are missing or incomplete, by testing.
The building’s operation and maintenance manual or health and safety file can record the slab thickness, concrete specification, reinforcement and ground conditions. Where these are not available, or the floor has been altered since construction, the following methods are used:
- Core samples. Cylinders of concrete drilled from the slab show its thickness and are tested for compressive strength. Cores are taken and tested to BS EN 12504-1, and in-situ strength is assessed to BS EN 13791. Cores are taken at representative locations, not at highly stressed points.
- Radar surveys. Ground-penetrating radar estimates slab thickness, locates reinforcement and identifies voids beneath the slab without breaking it out.ย The Concrete Society notes that interpretation “must be undertaken by a specialist”
- Ground investigation. A Standard Penetration Test (SPT) is an in-situ geotechnical test used to assess the resistance of soil to penetration. It is undertaken to help determine the ground conditions and assess whether the soil can support the proposed loads from the mezzanine floors.
The extent of testing depends on how much is already known. A recent building with full records may need little or none. An older building with no records may need all three.
Before a mezzanine floor can be designed, it has to be clear what the existing concrete slab can carry. That is established in one of two ways. First, from the building’s records. And where those aren’t available, by testing.
Records come first. The building’s operation and maintenance manual, or its health and safety file, can show how thick the slab is, what concrete was used, whether it’s reinforced, and the ground conditions beneath it.
Where those records are missing, or the floor has been altered since it was built, there are three main methods.
The first is core sampling. Small cylinders of concrete are drilled out of the slab. They show how thick it is, and they’re tested to find out how strong the concrete is. Cores are taken from representative areas, not from points that are already highly stressed.
The second is a radar survey. Ground-penetrating radar can estimate the slab’s thickness, locate any reinforcement, and pick up voids underneath it… all without breaking the floor out. The results do need a specialist to interpret them.
The third looks below the slab. A ground investigation, using boreholes or trial pits, shows the type of soil, how much weight it can bear, and how likely it is to settle.
How much testing is needed depends on how much is already known. A recent building with full records may need little or none. An older building with no records may need all three.
Either way, the answer shapes the design, so it’s worth establishing early.
What happens if the slab is not strong enough?
The strength of the slab sets how far apart the mezzanine columns can be.
Wider column spacing means fewer columns but a heavier load on each one. A strong slab allows a wider grid, which leaves more open space beneath the mezzanine. A weaker slab needs columns closer together so that each carries less.
Base plate size works in the same way. A larger plate spreads the column load over more concrete and reduces the pressure on the slab. Column positions are also adjusted to keep bases away from slab joints and edges where possible. The column layout is therefore a balance between what the slab can carry and how the space beneath the mezzanine needs to be used.
Are older buildings more likely to need slab work?
Older buildings are more likely to need slab assessment and strengthening, because their floors were not designed with mezzanine point loads in mind and their records are often incomplete.
A slab built for general storage or light manufacturing can have been designed only for loads spread across its surface. Records may be missing, the floor may have been patched or altered, and the ground beneath may be made ground or reclaimed land with an unknown history. Clay soils add a further risk.ย The British Geological Surveyย notes that “swelling pressures can cause heave, or lifting of structures, whilst shrinkage can cause settlement or subsidence”.
None of this rules out a mezzanine in an older building. It means the assessment needs to be more thorough, and the budget should allow for testing and possible remedial work from the outset.
Does a second tier change the answer?
A second mezzanine tier increases the load at each column base, so a slab adequate for a single tier is not automatically adequate for two. The slab is frequently the limiting factor on multi-tier installations and should be assessed before a second tier is specified.
What does a slab assessment not tell you?
A slab assessment confirms whether the floor can carry the mezzanine’s column loads. It does not confirm everything about the condition of the floor.
- Core tests measure compressive strength. BS EN 13791 states that it “does not include the assessment of the quality of concrete for properties other than compressive strength”.
- Tests sample a small number of locations. Where conditions vary across the building, the results are extrapolated, and engineers allow for that uncertainty.
- Crack repairs do not restore lost capacity. The Concrete Society states that crack repair “should be regarded as being required for serviceability purposes only”.
The assessment applies to the loads it was based on. A later change of use, heavier stock or new equipment on the mezzanine requires the slab to be checked again.
FAQs
A mezzanine floor is an intermediate raised platform inserted between the floor and ceiling of an existing building. It typically uses structural steel columns and beams, a deck (often timber decking), stair access, edge protection (handrails, barriers) and sometimes walls or partitions. It doesnโt constitute a full storey in legal terms but adds significant usable floor area internally without altering the building footprint.
Hi-Level Mezzanines designs and installs bespoke mezzanine floors for large-scale commercial and industrial projects.
- Planning and Installation
- Sectors and Applications