What should be included in a mezzanine floor quote?

Summary

A complete mezzanine floor quote defines exactly what will be built, what services are included, what is excluded or assumed, and the commercial terms. That means the floor’s size, design load and decking; stairs, guarding and fire protection; design, calculations and building regulations approval; installation and site work; the documents handed over at completion; and the price basis, payment terms, programme and warranty. Comparing quotes on these points, not on headline price alone, shows wh

Contents

Why does the content of a quote matter more than the price?

The content of a quote matters more than the price because two quotes for the same floor can cover very different scopes.
One quote may include fire protection, building regulations fees and slab investigation, while another excludes them or covers them with assumptions. The lower figure is not necessarily the cheaper project once the excluded items are added back. A quote that sets out its scope, exclusions and assumptions clearly makes the real cost visible before a contract is signed, and reduces the risk of price changes once work has started.

What should a quote say about the floor itself?

A quote should describe the floor precisely enough that the buyer can confirm it matches the requirement.

  • Dimensions. Length, width, total area and position in the building.
  • Headroom. The clear height expected beneath the deck and above it.
  • Design load. The imposed load the floor is designed for, the use it is based on, and any allowance for racking, equipment or other concentrated loads. This is the single most important figure for comparing quotes.
  • Decking. The deck material and thickness, and its suitability for the intended use.
  • Columns and slab. The column grid and any assumptions about the existing slab.
  • Steel standard. The standard the steelwork is made to. Fabricated structural steel delivered to site in Great Britain must be UKCA or CE marked against BS EN 1090-1. Steelconstruction.info notes that for most UK buildings execution class EXC2 under BS EN 1090-2 is appropriate.

What should a quote say about access and safety items?

A quote should state whether fire protection is included and, if so, exactly what it covers.

Fire protection is commonly provided by a fire-rated suspended ceiling beneath the deck, column casings, fascia along the exposed edges, and, where needed, enclosed staircases. The quote should state the fire resistance period the protection achieves, typically 30 or 60 minutes. It should also say whether any changes to existing sprinklers, fire detection or alarms are included, because these are often priced separately or left to the building owner.

What should a quote say about fire protection?

Several approvals and checks outside building regulations can add weeks or months to a project, and some have no fixed timescale.
Landlord consent. In a leased building, the landlord’s consent is usually needed. The law requires that consent is not unreasonably withheld, but sets no time limit for giving it.

  • Asbestos survey. HSE guidance is that a refurbishment survey is needed before work begins, and that it should be built into the planning phase “to avoid delays”. If asbestos must be removed by a licensed contractor, the enforcing authority must be notified at least 14 days before the removal starts.
  • Slab assessment. Where the slab’s capacity is unknown, testing and any ground investigation must be completed before the design can be finalised.
  • Planning permission. Most warehouse and factory mezzanines do not need planning permission. In retail premises, a mezzanine adding more than 200 square metres does, and the planning authority has eight weeks to decide, or 13 weeks for major development.
  • HSE notification. Larger projects must be notified to the Health and Safety Executive before construction starts.

What design and approval work should be included?

A quote should state who carries out the structural design and who obtains building regulations approval.

  • Design. Structural calculations and drawings for the mezzanine.
  • Slab and ground. Any slab assessment, testing or ground investigation, or a clear statement that it is excluded.
  • Building regulations application. For a workplace, building regulations approval in England requires a full plans application, because the building is covered by the Regulatory Reform (Fire Safety) Order 2005. The quote should state who submits the application.
  • Building control fees. Building control charges are payable to the local authority or registered building control body. The quote should state whether they are included.
  • Completion certificate. On completion, building control issues a completion certificate confirming the work complies with the regulations.

What installation and site work should be included?

A quote should describe how the floor will be installed and what site work is included.

  • Installation. Delivery, offloading, installation and removal of waste.
  • Working conditions. The working hours assumed, whether the operation continues during installation, and any phasing.
  • Foundations. Any slab works, pad foundations or piling, or a statement that they are excluded.
  • Building services. Changes to lighting, power, heating or sprinklers beneath or above the floor.
  • Health and safety roles. Under the Construction (Design and Management) Regulations 2015, where more than one contractor is involved, the client must appoint a principal designer and a principal contractor in writing. The quote should say whether the supplier will take on either role, and the principal contractor must prepare a construction phase plan.

What should be handed over at completion?

A quote should list the documents the buyer will receive when the work is finished.

  • The building regulations completion certificate.
  • The health and safety file, which the principal designer or principal contractor must pass to the client at the end of the project.
  • As-built drawings and structural calculations.
  • Load notices fixed in position.
  • Declarations of performance or certificates for the structural steel and fire protection products.
  • Guidance on inspection and maintenance.

What commercial terms should be clear?

A quote should make clear what the price covers, how it will be paid and what happens if things change.
Price basis. Which items are fixed price and which are provisional sums to be adjusted later.

  • VAT. HMRC guidance states that work to an existing building is “normally standard-rated”, so VAT at the standard rate applies to most commercial mezzanine installations.
  • Payment terms. Stage payments, deposits and timings. The Housing Grants, Construction and Regeneration Act 1996 requires construction contracts to “provide an adequate mechanism for determining what payments become due under the contract, and when”.
  • Retention. Any retention held back from payments. Government research in 2017 found retention is typically 5%, with half released at completion and half after a defects period of typically 12 months.
  • Programme and validity. Lead time, installation duration and how long the price remains valid.
  • Warranty. What is covered, for how long and by whom.

How should mezzanine quotes be compared?

Mezzanine quotes should be compared on scope first and price second.

Lining quotes up against the same list of items shows which ones are included, excluded or covered by an assumption. The most useful comparisons are usually the design load, the decking, the fire protection, the number of staircases, building regulations fees, slab and foundation work, and the treatment of building services. Where one supplier includes an item and another excludes it, adding an allowance for the missing item puts the quotes on the same basis. Quotes based on the same brief and the same building information are easier to compare than quotes based on each supplier’s own assumptions.

Transcript

When mezzanine floor quotes arrive, it’s natural to look at the price first. But the most reliable way to compare them is the other way round. Scope first, price second.

That’s because two quotes for the same floor can cover very different things. One might include fire protection and building regulations fees. Another might leave them out, or cover them with an assumption.

So start by lining every quote up against the same list of items. For each one, note whether it’s included, excluded, or based on an assumption.
Some items make more difference than others. The design load is the single most important figure, because it sets what the whole structure is built to carry. After that, look closely at the decking, the fire protection, the number of staircases, building regulations fees, any slab or foundation work… and what happens to building services, such as sprinklers and lighting.

Watch for provisional sums too. These are allowances that get adjusted later, so they aren’t fixed prices.
Where one supplier includes an item and another doesn’t, add an allowance for it to the quote that left it out. That puts both on the same basis.
And the comparison is far easier if every supplier starts from the same brief and the same information about the building. Then the differences that remain are real differences, not different assumptions.

Only then does the headline price tell you something useful.

What does a quote not guarantee?

A quote reflects the information available when it is prepared. It does not guarantee:

  • That building regulations approval will be granted without changes, until the application has been approved.
  • That ground or slab conditions match the assumptions made, until they have been investigated.
  • That the price will hold if the use, loads or layout change after the quote is given.
  • Contractual protection. A quote is not a contract until terms have been agreed and accepted.

FAQs

  • A mezzanine floor is an intermediate raised platform inserted between the floor and ceiling of an existing building. It typically uses structural steel columns and beams, a deck (often timber decking), stair access, edge protection (handrails, barriers) and sometimes walls or partitions. It doesnโ€™t constitute a full storey in legal terms but adds significant usable floor area internally without altering the building footprint.

    Hi-Level Mezzanines designs and installs bespoke mezzanine floors for large-scale commercial and industrial projects.

    • Planning and Installation
    • Sectors and Applications
    Copy link

Related Resources

Contact Us

Enquiry Form

Quote Request

Quote Request

Your Details


Supporting Files

Please attach any supporting drawings, plans and photographs that may be of assistance to us in preparing your quote. Simply click on the choose files button below to locate these files on your computer or network.