What are the stages of a mezzanine floor project?
A mezzanine floor project moves through five stages, and the total timescale depends on how long each one takes and how many can overlap.
- Enquiry and survey. The supplier gathers the requirements and surveys the building, including the available height, column positions and the existing slab.
- Design and quotation. The structure is designed for the intended use and loads, and a quote is prepared.
- Approvals. Building regulations approval, and any other consents such as the landlord’s, are obtained.
- Manufacture. Steel components are fabricated off site to the approved design.
- Installation and handover. The floor is installed, fire protection and access items are fitted, building control inspects the work, and the floor is handed over.
How long does installation take?
Installation of a simple single-tier mezzanine of moderate size can be completed within a few weeks of the order, while larger and more complex installations take several months. The main factors are:
- Size. The floor area and the number of tiers.
- Complexity. Higher loads, integration with conveyors or automation, and office fit-out add time.
- Ancillary items. Staircases, goods lifts, partitions and fire protection are fitted after the main structure.
- Site conditions. Restricted delivery times, limited access for vehicles and plant, and the need to phase work around a live operation all extend the programme.
- Foundation work. Slab strengthening, pad foundations or piling must be completed before the steel can go in.
How long does building regulations approval take?
In England, building control must decide a full plans application within five weeks of receiving it, unless a longer period is agreed in writing.
A mezzanine in a workplace requires a full plans application. The key timescales under the Building Regulations 2010 are:
- Decision. Within five weeks of the application, or a longer period agreed in writing. Building control not responding within the period does not count as approval.
- Notice of start. At least two days’ notice must be given before work starts.
- Lapse. Approval lapses if work does not start within three years.
- Completion. Notice must be given within five days of the work being completed, and building control must issue a completion certificate within eight weeks of that notice.
These rules changed in October 2023 under the Building Safety Act 2022. Earlier references to a two-month maximum for decisions no longer apply in England.
Which other approvals and checks affect the timescale?
Several approvals and checks outside building regulations can add weeks or months to a project, and some have no fixed timescale.
Landlord consent. In a leased building, the landlord’s consent is usually needed. The law requires that consent is not unreasonably withheld, but sets no time limit for giving it.
- Asbestos survey. HSE guidance is that a refurbishment survey is needed before work begins, and that it should be built into the planning phase “to avoid delays”. If asbestos must be removed by a licensed contractor, the enforcing authority must be notified at least 14 days before the removal starts.
- Slab assessment. Where the slab’s capacity is unknown, testing and any ground investigation must be completed before the design can be finalised.
- Planning permission. Most warehouse and factory mezzanines do not need planning permission. In retail premises, a mezzanine adding more than 200 square metres does, and the planning authority has eight weeks to decide, or 13 weeks for major development.
- HSE notification. Larger projects must be notified to the Health and Safety Executive before construction starts.
Which stages can run at the same time?
A project moves faster when the checks that do not depend on the final design are started at the same time as the design.
- The asbestos survey, slab assessment and request for landlord consent can usually start as soon as the outline scheme is agreed.
- The building regulations application can be submitted once the structural design is complete, rather than waiting for every detail of the fit-out.
- Building services changes, such as extending sprinklers or lighting, can be designed while the steel is being manufactured.
Stages that depend on earlier decisions cannot be overlapped safely. The steel cannot be manufactured until the design reflects the confirmed loads and the slab’s capacity, because changes after fabrication are slow and expensive.
A mezzanine floor project moves faster when the work that doesn’t depend on the final design is started at the same time as the design itself.
Three checks are good examples. The asbestos survey. The slab assessment. And the request for the landlord’s consent, if the building is leased.
Each of these can usually start as soon as the outline scheme is agreed. And each is worth starting early. An asbestos survey is needed before work begins. Testing the slab has to be finished before the design can be finalised. And there’s no set time limit for a landlord to give consent.
Next, the building regulations application. It can be submitted once the structural design is complete. There’s no need to wait for every detail of the fit-out to be settled.
Then, while the steel is being manufactured, changes to building services can be designed alongside it. Extending sprinklers or lighting, for example.
But not everything can overlap.
Some stages depend on decisions made earlier, and those can’t be rushed safely. The clearest example is the steel. It can’t be manufactured until the design reflects the confirmed loads… and what the slab can carry. If either changes after fabrication, putting it right is slow and expensive.
So the quickest projects aren’t the ones that rush. They’re the ones that start the right checks early, and fix the design before the steel is made.
What extends a mezzanine project the most?
Projects are extended most often by decisions or information that arrive late, rather than by the installation itself.
- A brief that changes after design has started, particularly the intended use or loads.
- Slab or ground problems discovered after the design is fixed.
- Fire safety and building regulations requirements considered late in the design.
- Landlord or third-party approvals that take longer than expected.
- Site restrictions, such as delivery hours, access or peak trading periods, that were not built into the programme.
When should a project start to meet a deadline?
A project should start early enough that approvals, checks and manufacture are complete before the installation window opens.
Working backwards from the date the floor is needed is the most reliable approach. The installation period is fixed by the operation, such as before a peak season or a lease date, so the approvals and checks need to fit in before it. Where the building is leased, the slab is unknown or the building was built before 2000, extra time should be allowed for consent, testing and surveys.
Which parts of the timescale cannot be predicted in advance?
Some parts of a mezzanine project’s timescale cannot be fixed until the relevant information is known.
- Ground and slab conditions, and whether foundations or piling are needed, are only known after investigation.
- Building control can request changes or further information, and the decision period can be extended by agreement.
- Landlord consent has no statutory deadline.
A programme given before these points are settled is an estimate. It becomes firm once the survey, slab information and approvals are in place.
FAQs
A mezzanine floor is an intermediate raised platform inserted between the floor and ceiling of an existing building. It typically uses structural steel columns and beams, a deck (often timber decking), stair access, edge protection (handrails, barriers) and sometimes walls or partitions. It doesnโt constitute a full storey in legal terms but adds significant usable floor area internally without altering the building footprint.
Hi-Level Mezzanines designs and installs bespoke mezzanine floors for large-scale commercial and industrial projects.
- Planning and Installation
- Sectors and Applications